Scope of Services: Owner Representation / Construction Management
Size: East and West Terminals including 34,000 sf of concessions
Project Cost: $450,000,000
Project Role: Owner Representative Partner / Turner Construction
Project Completion: August 2020
Project Owner: Broward County Aviation Department
Key Personnel: Wayne Messam
Angela Messam
Peter Codrington
This complicated project includes the expansion of Terminal 4 east and west concourses. As the Construction Project Management Team/Owner Representative, we are responsible for managing two separate construction managers at risk, Balfour Beatty and MCM, to ensure the project is built to BCAD, Department of Homeland Security and FAA specifications. Messam provides a Project Engineer, Superintendent and a Document Control Manager as a part of the Owner Rep Team with Turner Construction.